Hochofen 5A - EKO Stahl (Belgium)

Client EKO Stahl, Arcelor Group EKO Stahl
Industry Steel
Start 08 / 1994
End 12 / 1994
Budget  
     
Project Scope

Complete Project Preparation
Technical definition
Interface Cockerill Sambre
Co-ordination of the civil and erection works
Site co-ordination
Project documentation
Project administration
IPS Scope

D003/D004:
Time schedule
Technical co-ordination
Interface Cockerill Sambre
Co-ordination of the civil and erection works (part)
Site co-ordination (part)
Project documentation

D007:
Project administration
Description

Construction of a blast furnace with gas epuration unit, 2 casting platforms, INBA granulation unit, material handling and mixing, 4 cowper units and new water clearing unit, Capacity : 4100T/day.

Product description:

The blast furnace is where the iron is extracted from the iron ore. Solid ore and coke are fed into the furnace from the top, while a stream of very hot air (1,200° C) from the bottom causes the combustion of the coke, with its virtually pure carbon content. This produces carbon oxide, which "reduces" the iron oxide by removing oxygen, separating the iron. The heat created by the combustion melts the iron and gangue (aggregates of minerals in an ore) into a liquid. The gangue, being lighter, floats to the surface of the molten iron, known as "pig iron". Slag, which is the residue created by the molten gangue, can be used in other industrial applications, like road construction or cement production.

EKO Stahl